This page was exported from Valid Premium Exam [ http://premium.validexam.com ] Export date:Fri Sep 20 0:49:08 2024 / +0000 GMT ___________________________________________________ Title: [Sep-2022] C_TS422_2020 Dumps are Available for Instant Access from ValidExam [Q11-Q27] --------------------------------------------------- [Sep-2022] C_TS422_2020 Dumps are Available for Instant Access from ValidExam Study resources for the Valid C_TS422_2020 Braindumps! NEW QUESTION 11A planner wants to interactively resolve an overload situation on a resource using advanced planning tools without any automatic rescheduling activity by the system.Which combination of settings for resource and detailed scheduling strategy are required to receive related alerts?  Infinite resource and infinite strategy  Finite resource and finite strategy  Finite resource and infinite strategy  Infinite resource and finite strategy NEW QUESTION 12How can you carry out cost object controlling for production orders? Note: There are 2 correct answers to this question.  Cost-related  Order-related  Milestone-related  Product-related NEW QUESTION 13What does it mean for the production planner when MRP works with infinite capacities?  MRP assigns capacity requirements automatically to work center is with the earliest available capacity.  MRP creates capacity requirements without checking the capacity of a work center.  MRP creates capacity requirements only if the work center has sufficient capacity.  MRP assigns capacity requirements automatically after the last scheduled order on a work center. NEW QUESTION 14A material has been set up as a phantomassembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?  Change the item category of the phantom assembly in the BOM.  Change the explosion type of the phantom assembly in the BOM.  Change the phantom item indicator for the phantom assembly in the BOM.  Change the special procurement key of the phantom assembly in the BOM. NEW QUESTION 15Your client is asking for your advice on material master numbering in SAP S/4HANA. What do you need to consider? Note: There are2 correct answers to this question.  The display template for material numbers applies to all clients.  The number of leading zeros for internal numbers is client-specific.  The maximum mater all number length is 40 for external numbers and 18 for internal numbers.  In Customizing you can decide by material type whether to use the long material number. NEW QUESTION 16Which task list types can have parallel sequences? There are 2 correct answers to this question.  Routings (N)  Master recipes (2)  Rate routings (R)  Reference operation sets (S) NEW QUESTION 17Where does the system check master data selection settings during the creation of planned orders and production orders? Note: There are 3 correct answers to this question.  In the production version  In the production order type  In the routing  In the bill of materials (BOM)  In the MRP controller NEW QUESTION 18Which of the following functions can be performed when the production order has the status “Created” (CRTD)? Please choose the correct answer.  A user can trigger material staging via mass processing (transaction COHV).  A user trigger printing of shop floor paper manually (transaction CO02).  A user trigger material availability check via mass processing (transaction COHV)  A user can schedule a background job to release production orders (transaction COOIS). NEW QUESTION 19For what production type are production orders used?  Period and quantity-oriented production  Replenishment controlled by control cycles  Process manufacturing processes  Discrete manufacturing processes NEW QUESTION 20What could be the reason for multiple commitment of individual capacities, where several operations have the same scheduled dates on a resource after capacity planning? Note: There are 2 correct answers to this question.  Alternative resources are fully occupied.  The Change Planning Direct on indicator is set.  The work center has several individual capacities.  The planning strategy is infinite. NEW QUESTION 21How can you set up the supply source for the SAP Kanban process? Note: There are 3correct answers to this question.  Using purchase orders for external procurement  Using stock transfer reservations for stock transfer  Using run schedule quantities for in-house production  Using purchasing costs for automated source prioritization  Using quotations for internal and external procurement NEW QUESTION 22You are creating a production order manually. What activities are involved in this process?There are 3 correct answers to this question.  Planning selection  Order type determination  Actual cost calculation  Capacity requirements determination  Master data selection NEW QUESTION 23What are the possible categories for the Business Partner master data object in SAP S/4HANA?There are 3 correct answers to this question.  Organization  Customer  Person  Vendor  Group NEW QUESTION 24Why would you use phantom assemblies? Note: There are 3 correct answers to this question.  To make the assignment of components easier  Tosimplify the structure of bills of material  To reduce the number of changes required in bills of material  To increase the number of planning levels  To reduce the number of material masters NEW QUESTION 25In which customizing activity do you set up automatic routing selection production orders?Please choose the correct answer.  Define order-type-dependent parameter  Define scheduling parameters for production orders  Define selection profiles  Define production scheduling profile NEW QUESTION 26Which of the following elements does MRP take into account during net requirement calculation? Note: There are 2 correct answers tothis question.  Maximum stock level  Purchase orders  Safety stock  Lot size NEW QUESTION 27You run MRP for a material that was planned using Demand-Driven Replenishment. Toward which buffer level does the MRP run create a replenishment proposal?  Top of Red Base  Top of Red  Top of Green  Top of Yellow  Loading … Updated C_TS422_2020 Tests Engine pdf - All Free Dumps Guaranteed: https://www.validexam.com/C_TS422_2020-latest-dumps.html --------------------------------------------------- Images: https://premium.validexam.com/wp-content/plugins/watu/loading.gif https://premium.validexam.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2022-09-29 16:53:32 Post date GMT: 2022-09-29 16:53:32 Post modified date: 2022-09-29 16:53:32 Post modified date GMT: 2022-09-29 16:53:32