NEW QUESTION 90
An architect is tasked with updating the design of an existing vSphere-based solution for a pharmaceuticals customer. The update will include upgrade to VMware vCenter 8 and VMware vSphere 8 and the creation of a new cluster that will be used for ongoing research projects. The research project that is driving the need for an update includes a number of applications that are latency-sensitive.
The customer has confirmed the following information during the initial workshop:
The customer recently completed a right sizing exercise using VMware Aria Operations that resulted in a number of ESXi hosts becoming available for use.
Each of the VMware ESXi host servers is configured with:
— 2 x 20-core Intel Xeon CPU sockets
— 1024 GB RAM divided evenly between sockets
There is no additional budget for purchasing hardware.
After confirming the existing hardware is still listed on the VMware Hardware Compatibility List (HCL), the architect makes the following design decisions with regard to the workload design:
The solution will support a maximum of 20 combined cores and sockets per virtual machine.
The solution will support a maximum of 512 GB RAM per virtual machine.
What should the architect document as justification for these design decisions?

 
 
 
 

NEW QUESTION 91
What are workload design requirements related to?

 
 
 
 

NEW QUESTION 92
Which is a benefit of using vSAN stretched clusters in VMware Cloud Foundation?

 
 
 
 

NEW QUESTION 93
An architect is designing a new VMware software-defined data center (SDDC) that will consist of
100 branch sites connected to a single VMware vCenter Server within the primary data center. To allow for the use of existing automation scripts, there is a requirement to replicate the names of the virtual distributed port groups across all sites. The procurement team purchases licensing and there is no further budget allocated.
Which design decision should the architect make to meet this requirement?

 
 
 
 

NEW QUESTION 94
A customer is deploying a new cluster and wants to be able to patch and update two hosts in parallel. The cluster must be able to maintain N+1 resiliency across the remaining hosts while patching activities are performed. The current expected utilization of the platform requires a minimum of two hosts to support all of the virtual machines.
What is the minimum number of hosts the customer will require in the cluster in order to meet the required resiliency level?

 
 
 
 

NEW QUESTION 95
What are assumptions in the context of design?

 
 
 
 

NEW QUESTION 96
An architect is designing a new vSphere environment to meet the following requirements:
– The environment must support 5,000 virtual machines.
– The environment will be built initially using 350 hosts.
Which vCenter Server appliance deployment size should the architect specify for the design?

 
 
 
 

NEW QUESTION 97
An architect is documenting the design for a new vSphere cluster. The customer provides the following information:
All ESXi hosts will use hardware from the same vendor
All ESXi hosts will be monitored for hardware related issues using the vendor’s monitoring tooling The vendor’s monitoring tooling provides a plugin for vCenter to allow the hardware status to be visible The customer also informs the architect of the following requirements:
Workloads must be automatically relocated to other hosts in the event that a host hardware is marked as degraded.
Workloads must be automatically restarted on other hosts in the event of a host failure.
What should the architect include in the design to meet these requirements?

 
 
 
 

NEW QUESTION 98
In the context of the AMPRSS framework, what does “Manageability” refer to?

 
 
 
 

NEW QUESTION 99
An architect is designing a new vSphere environment with the following resources:
– 600 vCPU
– 5,760 GB RAM
Average resource usage is:
– 60 vCPU
– 1,152 GB RAM
The design must meet the following requirements:
– The environment has the ability to burst by 25%.
– Each host can schedule 36 vCPUs and has 512 GB RAM.
– Management overhead is 20%.
What is the minimum number of hosts required to meet the design requirements?

 
 
 
 

NEW QUESTION 100
What does the term “Recoverability” refer to in the AMPRSS framework?

 
 
 
 

NEW QUESTION 101
What do availability requirements for vCenter Server relate to?

 
 
 
 

NEW QUESTION 102
How do you determine storage topology needs for a vSphere design?

 
 
 
 

NEW QUESTION 103
What does “Scalability” mean in the context of the AMPRSS framework?

 
 
 
 

NEW QUESTION 104
A VMware Service Provider is tasked with delivering a solution for continuous availability for a subset of Tier 1 virtual machines (VMs) and vApps running in their vSAN environment. The VMs make up a mission-critical application and there can be no data loss in the event of an outage at their primary data center.
In the event of a regional outage, they have established a 10-minute recovery point objective (RPO).
Failover/failback to the third site must be automated.
They have the following in place:
– Two local data centers (primary and secondary) connected with 100 Gb dedicated fiber
– 2ms round-trip time (RTT) latency between the sites
– A third data center located on another power grid
– 70ms latency between the primary and secondary data centers
– Matching storage arrays at all locations.
Which two solutions could be used to meet the requirements? (Choose two.)

 
 
 
 
 

NEW QUESTION 105
An architect is designing a solution for an environment with a limited number of operating system licenses.
How should the architect design the virtual infrastructure to meet the operating system license requirements?

 
 
 
 

NEW QUESTION 106
Following a recent acquisition, the architect learns that both companies use vSphere on-premise and will need to combine the data centers into one. The acquired company’s licenses will not be renewed for cost-savings related to the acquisition. All consumed vSphere licenses must have active support to support line-of-business operations. The merged environment must maintain
25% spare capacity. The architect has a small budget remaining unallocated for hardware.
The architect has calculated that the current vSphere environment can absorb the acquired company’s virtual machines but the cluster will run at 90% memory utilization and at 50% CPU utilization.
Which design decision can the architect make to incorporate the new company’s virtual machines into the combined vSphere environment?

 
 
 
 

Fully Updated Free Actual VMware 3V0-21.23 Exam Questions: https://www.validexam.com/3V0-21.23-latest-dumps.html

         

Related Links: www.stes.tyc.edu.tw myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt www.stes.tyc.edu.tw

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below